CAT 2021 Slot 2 · Quant · Time and Work · medium

A is thrice as efficient as B, and working together they can complete a job in 12 days. B starts the job alone and works for 8 days, after which A…

Single correct option

A is thrice as efficient as B, and working together they can complete a job in 12 days. B starts the job alone and works for 8 days, after which A joins him and they finish the remaining work together. In how many days, from the start, is the job completed?
  1. A. 16
  2. B. 18
  3. C. 20
  4. D. 22
Show answer and solution

Answer: (B) 18

Let B's rate = r, so A's rate = 3r. Together: 4r = 1/12 ⇒ r = 1/48.

So B alone would take 48 days, and A alone would take 16 days.

In the first 8 days, B alone does 8 × (1/48) = 1/6 of the job, leaving 5/6.

Once A joins, their combined rate is again 4r = 1/12 per day, so the remaining 5/6 takes (5/6) ÷ (1/12) = 10 days.

Total time = 8 + 10 = 18 days.

Tip: the combined rate after A joins is the same 'together' rate given at the start — no need to recompute it.