PrepRung

CAT 2023 Slot 1 · Quant · Time and Work · medium

A can complete a piece of work in 18 days and C can complete it in 24 days. In how many more days will C alone finish the remaining work?

Single correct option

A can complete a piece of work in 18 days and C can complete it in 24 days. They work together for 6 days, after which A leaves. In how many more days will C alone finish the remaining work?
  1. A. 8 days
  2. B. 9 days
  3. C. 10 days
  4. D. 12 days
Show answer and solution

Answer: (C) 10 days

A's rate = 1/18, C's rate = 1/24 per day. Together, work done in 6 days = 6×(1/18+1/24) = 6×(4/72+3/72) = 6×(7/72) = 7/12. Remaining work = 1 − 7/12 = 5/12. C alone takes (5/12) ÷ (1/24) = 10 days to finish the remaining work.